level 3 survey manchester

Level 3 Survey for 19th Century Property in Manchester

CJ Bloor | RICS Level 3 Building Survey — 6 Barton Street, Manchester
Survey typeRICS Level 3 Building Survey
Inspection dateJanuary 2026
EPC ratingE — 49 (below national average)

Overall opinion: The property is considered to be a reasonable purchase although there are a number of defects which require attention, and which will require some expenditure at the outset. You should investigate the cost of these works prior to commitment to purchase. Once these works have been undertaken to a satisfactory standard, normal ongoing maintenance will be required to ensure that the property remains in satisfactory condition.

A
Property Overview
Key characteristics at the time of inspection
This section gives you a snapshot of what the surveyor found when they visited the property — the basics of how it's built, how many rooms it has, and what services are connected. This is a Victorian end-terraced property in Manchester city centre, built around 1840, so it behaves very differently to a modern home. The age and mixed construction mean damp resistance, thermal performance, and structural resilience require particular attention.
Front elevation of 6 Barton Street
Front elevation — 2-storey end-terrace, c.1840, solid/cavity masonry with timber cladding to rear
Property type
End-terraced
Two storey house
Bedrooms
1
First floor
Approximate age
c. 1840
Approx. 185 years old
Tenure
TBC
To be confirmed by solicitor

Construction

Front wallsSolid masonry, 260mm, uninsulated
Side/rear wallsCavity construction, c.300mm
Main roofDual-pitched, natural slate
Dormer roofFlat, GRP (fibreglass)
Internal wallsSolid / timber stud, plaster finish
FloorsSolid (GF) / suspended timber (FF)

Accommodation

Ground floor1 bedroom, 1 bathroom
First floor1 lounge, 1 kitchen
BalconiesFront and rear terraces, timber decked
OrientationFaces approximately east
LocationDeansgate-Castlefield, Manchester city centre
ParkingNo off-road parking; double yellow lines
No gas (electric only)
Electricity connected
Mains water
Mains drainage

Survey photographs — external

Natural slate roof
Main roof: natural slate & flat GRP dormer — Rated 2
Verge without over-sail / rotten timbers
Rear verge: no over-sail; timber rot — Rated 2
Frost-damaged brickwork and open mortar joints
Front elevation: open mortar joints & frost damage — Rated 2
B
Condition Ratings
All surveyed elements grouped by urgency
The RICS condition rating system is a straightforward traffic-light style score. Rating 3 = urgent action required — these are serious defects or safety risks needing immediate attention. Rating 2 = attention needed, but not an emergency. Rating 1 = no current repairs needed — maintain in the normal way. Obtain quotes for all items rated 2 or 3 before exchanging contracts.
3
Urgent — serious defects
2
Attention needed
1
No current issues
3
Other joinery & finishes
D8 — Timber decay to rear eaves boards; urgent replacement required
3
Walls and partitions
E3 — Elevated moisture in bedroom rear corner; penetrating damp confirmed
3
Woodwork / staircase joinery
E7 — Elevated moisture & water damage to hallway skirting; investigation required
3
Electricity
F1 — No electrical safety certificate; full inspection by registered electrician required
2
Roof coverings
D2 — Moss; inadequate over-sail to rear verges; parapet flashings to check
2
Rainwater pipes & gutters
D3 — Rear gutter terminates short; stop-end missing; front hopper blocked
2
Main walls
D4 — Cracking; frost damage; moss; timber cladding; DPC issues; water staining
2
Windows
D5 — Single-glazed lounge window; trickle vent guard missing
2
Outside doors
D6 — Loose glazing seal to rear balcony door; flaking paintwork to rear sill
2
Ceilings
E2 — Historic water staining to lounge ceiling at parapet wall junction
2
Floors
E4 — First floor boards slightly loose/creaking in places
2
Built-in fittings
E6 — Flexible sealant partially absent around kitchen sink worktop
2
Other (E9)
E9 — Internal decorations worn; redecoration recommended
2
Grounds (balconies)
G3 — Front balcony decking in poor condition; prone to collapse; replace now
1
Bathroom fittings
E8 — Suite in serviceable condition; mechanical extraction installed
1
Water
F3 — Mains connected; copper pipework; pressure adequate
1
Heating
F4 — Wall-mounted electric heaters; serviceable
1
Water heating
F5 — Hot water cylinder in utility cupboard; serviceable
NI
Roof structure
E1 — Vaulted ceilings prevent inspection; assumed conventional construction
NI
Drainage
F6 — Assumed mains connection; underground drainage concealed
C
Key Concerns in Detail
Click any item to expand the surveyor's findings and recommendations
Each item tells you what was found, why it matters, and what you should do about it. Items marked Urgent should be investigated and quoted before you exchange contracts. Click each card to read the full detail.
UrgentElectricity — No safety certificate; full inspection required
Electric meter and consumer unit
Electric meter and consumer unit in the hallway cupboard — no evidence of recent safety inspection
The electricity meter is in the hallway cupboard and the consumer unit is in the utility cupboard. The wiring is of PVC covered cables with RCDs and MCBs for protection. There is no evidence that the electrical system has been tested within the last 12 months. You should instruct an appropriately qualified person to inspect the electrical installation prior to exchange, with allied repairs carried out as required. You should not use the electrical system until this is done. Thereafter, the installation should be retested every ten years. Your conveyancer should also establish that Building Regulation approval is in place for any rewiring works.
UrgentWalls — Elevated moisture in bedroom; penetrating damp
Water staining to lounge ceiling
Water staining to lounge ceiling — historic leak at front roof slope/parapet junction
Elevated moisture readings were recorded in the rear right-hand corner of the bedroom. In the surveyor's opinion, the dampness is the result of penetrating moisture caused by raised external ground levels which sit above the internal floor level, allowing moisture to bridge the damp-proof course. Specialist advice should be sought regarding an appropriate alternative method of damp control. Until the external works and DPC issues described in Section D4 are addressed, continued moisture ingress and further deterioration of internal finishes should be anticipated.
UrgentWoodwork — Moisture damage to hallway skirting; investigation required
Moisture meter reading to hallway skirting board
Elevated moisture reading (59.5) to hallway skirting — cause requires invasive investigation
Elevated moisture readings and visible water damage are noted to the skirting board in the hallway along the partition wall with the bathroom. It is not possible from a one-time inspection to confirm the precise cause, as several factors may be contributing — potential sources include a plumbing leak within the bathroom or capillary action where plaster skim is in direct contact with the solid floor. Further invasive investigation is required, including removal of the affected skirting board to assess the underlying plaster and check for concealed drainage or pipework. Once the cause has been identified and addressed, the damaged skirting board should be replaced.
UrgentJoinery — Timber decay to rear eaves boards; replace now
The boards at eaves level to the rear elevation are formed in timber decorated with a paint film. These were found to be in poor decorative order, and some sections have been affected by significant timber decay. The affected boards should be replaced, preferably in a non-maintenance material such as uPVC to prevent recurrence. If replaced in timber, they will remain vulnerable to further decay, particularly if gutter and roof leaks continue. This is directly linked to the inadequate over-sail of the roof verges described in Section D2 — both issues should be addressed together to prevent the cycle of moisture damage repeating.
AttentionMain walls — DPC issues, cracking, frost damage & water staining
Several issues affect the main walls. A chemically injected DPC has been installed to the front elevation but is positioned above the internal floor level, meaning it is unlikely to provide effective protection against rising damp. External ground levels are flush with the internal floor level, which increases this risk — lowering the ground level is impractical due to the public footpath. To the side/rear, ground levels are also above internal floor level. Localised open mortar joints, frost-damaged bricks and eroded masonry lintels are present to the original front elevation. Vertical cracking is noted at the side/rear abutment, consistent with differential settlement, and at the front balcony side elevation, consistent with thermal movement. Water staining is visible below both balconies due to insufficient overhang of the masonry copings. The rear timber cladding is in poor decorative order. All affected areas require repointing, brick repair, coping re-detailing, and specialist damp advice.
AttentionBalconies — Front deck in poor condition; prone to collapse
Rear balcony terrace with timber decking
Rear balcony terrace — decking serviceable but requires redecoration. Front balcony decking is in poor condition and prone to collapse.
The front balcony decking is in a poor condition and prone to collapse — this should be replaced now as a priority. The rear balcony decking is in a serviceable condition but requires periodic redecoration to preserve the timber. Balcony walls are generally serviceable but a minor overhaul is recommended, including removal of moss from the mortar joints to prevent further deterioration.
AttentionRoof — Moss, inadequate over-sail & gutter defects
The main roof is natural slate and in serviceable condition. However, several maintenance issues were identified. The verge slates to the rear slope do not project sufficiently beyond the timber barge boards, allowing rainwater to discharge directly onto the eaves joinery and causing the timber rot noted in D8. The roof covering should be extended to provide adequate over-sail. Moss growth is present at the parapet copings and at the junction with the dormer — this should be brushed clear and affected mortar joints repointed. The rear right-hand gutter terminates short of the verge slates, the stop-end is missing, and both the front hopper and rear gutter are partially blocked with moss — all should be cleared and extended. Regular inspection of the parapet flashings is essential to maintain weathertightness.
D
Environmental & Local Risk Factors
Issues your legal adviser should investigate before exchange of contracts
As well as the physical condition of the building, there are a number of external environmental factors that can affect the value, safety, or insurability of a property. Some require specific searches or specialist reports before you commit to buying. This section also flags important issues specific to this city-centre location.
Low risk

Flooding

According to the Environment Agency and Manchester City Council, the property is at very low risk of surface water flooding and a very low risk of flooding from rivers and seas.

Investigate

Former coal mining area

According to the Coal Authority, the property is in an area historically affected by mining activity. A mining report should be obtained by your legal adviser before exchange of contracts.

Nil risk

Radon gas

According to Public Health England, the property is not in an area with potentially high levels of radon gas. The risk level is <1% — no action required.

Nil risk

Clay subsoil

According to the Land Information System, the property is not in an area with clay sub-soils that could affect the stability of foundations. No specific subsidence risk identified.

Advisory

Asbestos

Given the property's age (c.1840), asbestos-containing materials may be present within the structure. Any suspected materials must be assessed before works are undertaken and removed only by a licensed contractor.

Note

Noise & disturbance

The property is in close proximity to bars, restaurants and nightclubs in Deansgate-Castlefield. Noise and disturbance should be anticipated and may affect your quiet enjoyment. Visit at different times of day before committing to purchase.

E
Energy Matters
Current EPC rating and key improvement recommendations
The EPC rates energy efficiency from G (very inefficient) to A (very efficient). This property currently sits at E-49, which is a poor rating — meaning it will be relatively expensive to heat, light and run. The solid front walls offer no insulation, the heating is electric only (generally more expensive to run than gas), and there are no renewable energy systems. Significant improvement is possible with the right investment.
Energy Performance Certificate (EPC) — dated 20th August 2020E — 49 (poor; below national average)
G — 1F — 20E — 39 ▲ This propertyD — 55C — 69B — 81A — 92+
🧱
Wall insulation (front)The front elevation is solid masonry with no cavity. Consider internal dry-lining with insulation board to reduce heat loss and risk of condensation.
🔥
Heating upgradeThe property is heated by wall-mounted electric heaters. These are expensive to run. Consider upgrading to a more efficient system when budget allows.
💧
Floor insulationGround floor is solid construction. First floor is suspended timber and could be insulated from below, subject to access.
💡
LED lightingReplacing all non-LED fittings will reduce electricity consumption and running costs.
☀️
Solar PVNo renewable energy systems are currently installed. Solar PV could help offset the higher running costs of electric heating. Roof structure would need checking first given the age of the building.
🖪️
Double glazing to loungeThe lounge currently has a single-glazed timber window. Upgrading to a modern double-glazed unit would improve both energy efficiency and acoustic comfort in this city-centre location.
F
Surveyor & Next Steps
Get in touch and work through your pre-exchange checklist

Wondering if you need a survey?

CJ Bloor Property Consultants Limited  |  RICS-regulated

Our team is happy to answer any questions, ensuring you get the right survey for your home.

[email protected]  |  www.cjbloor.co.uk

Pre-exchange action checklist

Before you legally commit to buying this property, ensure all of the following have been completed. Get at least two written quotes for any repair works and instruct only qualified, insured contractors.

Commission a full electrical inspection by a NICEIC/Part P registered electrician before exchange
Instruct a specialist to carry out invasive investigation of hallway skirting moisture (E7) to identify cause
Replace the front balcony decking as a priority — current condition is prone to collapse
Obtain quotes for rear eaves board replacement (timber decay — D8)
Seek specialist damp advice regarding DPC arrangements front and rear (D4 / E3)
Obtain quotes for repointing, brick repair and masonry lintel assessment (D4)
Clear all gutters and hoppers; extend rear gutter and install missing stop-end (D3)
Extend roof verge slates to provide adequate over-sail at rear; repair affected fascia/barge boards (D2)
Ask solicitor to confirm Building Regulation consents and guarantees for all significant works (H1 & H2)
Obtain a mining report through your legal adviser (coal mining area — I2)
Obtain building insurance quotes before exchange; ensure cover commences on exchange date
Refix or replace loose glazing seal to rear balcony door (D6)
Share the Post:

Related Posts